M.W. war bereits für Ende 2018 35 GWh Zellkapazität von Panasonic geplant. Jetzt wird dieser Wert wohl erst Ende März 2019 erreicht. Die Akkupack-Kapazität, also die Kapazität die Tesla gehört, war und ist wohl immer etwas höher und sollte auch Ende 2018 50 MWh erreichen.

Die mittelfristige Kapazität soll bei 105 an Zellen (Panasonic) bzw 150 GWh Akkupacks (Tesla) liegen.
MS90D, EZ10/2016
Benutzeravatar
 
Beiträge: 111
Registriert: 1. Dez 2016, 17:31
Wohnort: Heddesheim

Re: Tesla Gigafactory Zell- und Pack Produktion

von Bones » 13. Apr 2019, 23:27

https://twitter.com/elonmusk/status/111 ... 01056?s=20

Pana cell lines at Giga are only at ~24GWh/yr & have been a constraint on Model 3 output since July. No choice but to use other suppliers for Powerwall/Powerpack cells. Tesla won’t spend money on more capacity until existing lines get closer to 35GWh theoretical.
Dateianhänge
Screenshot_2019-04-13-23-25-45.png
24 GWh?
Benutzeravatar
 
Beiträge: 3542
Registriert: 20. Apr 2017, 08:07

Re: Tesla Gigafactory Zell- und Pack Produktion

von Bones » 25. Apr 2019, 07:05

Aus dem Q1/2019 update letter:

Energy storage production in the second half of 2018 was limited by cell production as we routed all available Gigafactory 1 cell capacity to supply Model 3. Some Gigafactory 1 cell production has been routed back to the energy storage business, enabling us to increase production in Q1 by roughly 30% compared to the previous quarter.
Benutzeravatar
 
Beiträge: 3542
Registriert: 20. Apr 2017, 08:07

Re: Tesla Gigafactory Zell- und Pack Produktion

von Bones » 25. Apr 2019, 12:17

Die neuen Linien von Panasonic in der GF1 sind wohl alle installiert, aber noch nicht voll im Einsatz.

via teslarati: klick
Panasonic [..........] , though it did confirm that it had completed the installation of new equipment in Gigafactory 1 that allows the facility to have a capacity of 35 GWh. Nevertheless, the Japanese company stated that for now, the newly-installed equipment is yet to enter full operation in Gigafactory 1. Tesla is yet to issue a statement on the recent Nikkan Kogyo report.


yahoo finance

Panasonic said it had completed installation of its equipment for a Nevada capacity of 35 GWh by the end of March 2019, but that not all the installed equipment is in full operation.
Benutzeravatar
 
Beiträge: 3542
Registriert: 20. Apr 2017, 08:07

Re: Tesla Gigafactory Zell- und Pack Produktion

von Teatime » 25. Apr 2019, 17:59

Panasonic kann wohl die Produktion der 18650er Zellen in Japan relativ einfach auf 2170er umstellen

The Japanese production lines would only need minor changes to switch to 2170 cells from the 18650
https://finance.yahoo.com/news/panasoni ... ccounter=1


Panasonic has decided to produce new batteries for electric vehicles (EVs) for the US Tesla at the Suminoe Plant (Suminoe Ward, Osaka). Negotiations with Tesla have been repeated, and production will begin by the end of 2019. For the time being, the company plans to produce a new battery only with the jointly operated Giga Factory (Nevada, USA). Panasonic has decided to offer Tesla, judging that the Japan-US bipolar production system, which can easily cope with fluctuations in demand, is the best while suppressing large-scale investment.
The Suminoe Plant (Suminoe Ward, Osaka City) currently produces the old cylindrical car battery "18650" for Tesla, and is used for EV "Model S" and "Model X" released before 15 years. . On the other hand, the "Model 3" launched in 17 years is called "2170", and a new battery with a large size and high energy density is adopted.
In the future, demand saturation is expected for models S and other models released before Model 3. The plant will have excess production capacity for old batteries, so some of the equipment can be changed to produce new batteries.
Currently, new batteries are being produced at the "Giga Factory", but it is said that Tesla's production volume of Panasonic's battery cells is insufficient, limiting the production of Model 3.
On the other hand, Panasonic plans to quickly shift to full production from the new line established at Giga Factory and respond to requests for increased production by improving existing lines. In addition, the Suminoe plant will also produce new batteries, and Tesla plans to secure sufficient production capacity even if the production of Model 3 is raised by 40% over the current level to over 7,000 units a week.

aus den Kommentaren
ogikubosuginami
https://www.teslarati.com/tesla-panason ... ls-source/
 
Beiträge: 606
Registriert: 25. Jul 2018, 17:01

Re: Tesla Gigafactory Zell- und Pack Produktion

von FFF » 25. Apr 2019, 22:13

Teatime hat geschrieben:Panasonic kann wohl die Produktion der 18650er Zellen in Japan relativ einfach auf 2170er umstellen

Spannender finde ich den Verweis auf "neue Batterien". Das würde sich damit decken, daß Musk ausdrücklich erklärt hat, das "FL2" für S und X würde nicht mit 2170er Zellen passieren...
LG
Karl
(75D seit 26.3.18 44500km, @2019.12.1.1 , 212Wh/km
 
Beiträge: 1314
Registriert: 7. Mär 2018, 16:13

Re: Tesla Gigafactory Zell- und Pack Produktion

von Teatime » 25. Apr 2019, 23:08

FFF hat geschrieben:
Teatime hat geschrieben:Panasonic kann wohl die Produktion der 18650er Zellen in Japan relativ einfach auf 2170er umstellen

Spannender finde ich den Verweis auf "neue Batterien". Das würde sich damit decken, daß Musk ausdrücklich erklärt hat, das "FL2" für S und X würde nicht mit 2170er Zellen passieren...

Genau deswegen habe ich den Kommentar von ogikubosuginami eingestellt :)
Thumbs up für´s genaue Lesen!
 
Beiträge: 606
Registriert: 25. Jul 2018, 17:01

Re: Tesla Gigafactory Zell- und Pack Produktion

von Bones » 3. Mai 2019, 18:20

CNBC Video aus der GF1

Aktuelles Bild-und Videomaterial.
Benutzeravatar
 
Beiträge: 3542
Registriert: 20. Apr 2017, 08:07

Re: Tesla Gigafactory Zell- und Pack Produktion

von Bones » 9. Mai 2019, 20:01

insideevs.com: panasonic financials

In terms of cylindrical cells at the Tesla Gigafactory in Nevada, Panasonic expressed the need to increase productivity and utilization. Hopefully, it will reach the promised 35 GWh annually.
###
"Improve profitability by increasing productivity and utilization at factory in North America."
####
Benutzeravatar
 
Beiträge: 3542
Registriert: 20. Apr 2017, 08:07

Re: Tesla Gigafactory Zell- und Pack Produktion

von Bones » 10. Mai 2019, 21:31

teslarati mit nem Auszug aus der FY 19 Q&A
Including the lines that have yet to start, we have three fast, higher speed lines, and when they become operational, we will see improved efficiency. And when we shifted tools, we were not really able to do sufficient verification of the facilities. We saw disruptions, and we now know the reasons. And so in June, we will start replacing the jigs, and therefore, the number of cells and the yield will improve quite a bit,” Tsuga said.